Where it’s at now
All the big pieces are here
17 November 2026
The second barge brought the last section of the fixed deck, joining the pylon and the other deck section at Warrenpoint Harbour, ready to be moved to the bridge site.
- Construction startsJune 2024
- Foundations complete2025
- Steel sections arrive from BelgiumOct–Nov 2026
- Pylon and fixed span lifted into placeNOWWinter 2026–27
- Opening span delivered and fitted2027
- Main construction completeLate 2027
- Testing, then open to trafficEarly 2028 (expected)
The engineering
How the bridge works
A leaning pylon
A tall steel pylon on the Louth side holds up the long fixed span with a fan of steel cables, a "cable-stayed" design.
A span that lifts
The shorter span on the Down side rolls up on a "rolling bascule" so boats can still reach Newry. Barriers stop traffic while it’s up.
Built in Belgium
The steel sections were made in Belgium and shipped by barge through the Dutch canals and across the North Sea to Warrenpoint.
The bridge in numbers
- long, in two spans
- ≈195mlong, in two spansA cable-stayed bridge across the Newry River at Narrow Water
- pylon
- 114mpylonThe length of the steel pylon as it arrived by barge
- deck section
- 690tdeck sectionOne of the two fixed-deck sections, 82 metres long
- delivery contract
- €102mdelivery contractPlus VAT, from the Irish Government’s Shared Island Fund
Progress in pictures
Watch it take shape


New photos are added as the bridge goes up. Got a great shot? Send it to us.
Progress diary
17 November 2026
All the big pieces are here
The second barge brought the last section of the fixed deck, joining the pylon and the other deck section at Warrenpoint Harbour, ready to be moved to the bridge site.
20 October 2026
Pylon and deck arrive from Belgium
The barge Caroline docked at Warrenpoint Harbour carrying the 114-metre pylon and an 82-metre, 690-tonne deck section, after five days at sea and through the Dutch canals. Lifting it all into place is expected to take eight to 12 weeks, depending on the weather.
1 September 2026
Big lift preparations
Temporary supports and a skid track went into the river to slide the huge sections into position, and part of the Carlingford Lough Greenway closed while the heavy work goes on.
12 June 2025
Foundations done
The Taoiseach visited the site as the foundation work was completed, with the contractors saying the bridge was on time and on budget.
4 June 2024
Work begins
The Irish and Northern Ireland governments marked the start of construction, decades after the idea was first proposed.
What it changes
Two shores, one short hop
Today, getting from Warrenpoint to Omeath or Carlingford means going round by Newry. Once the bridge opens it’s a few minutes across, by car, bike or on foot.
| Journey | Today | With the bridge |
|---|---|---|
| Warrenpoint → Omeath | ≈25 min by car via Newry | ≈10 min by car, or a pleasant cycle |
| Warrenpoint → Carlingford | ≈35 min by car via Newry | ≈20 min by car |
| Rostrevor → Carlingford | ≈40 min by car via Newry | ≈25 min by car |
Rough estimates, rounded, outside rush hour. Real times will depend on traffic and the bridge opening for boats.
A walking and cycling route, separated from traffic, with a ramp onto the Carlingford Lough Greenway.
Day trips that take in Warrenpoint, Rostrevor and Carlingford in one go.
No toll is currently planned. The bridge lifts now and then to let boats through.
Where to watch it being built
- Warrenpoint seafront and harbour: the barges from Belgium come into the harbour, and you can see across to the site.
- By Narrow Water Castle: the bridge lands right beside the castle. About the castle
- Please: stay out of the works area, park considerately, and check the project’s notices for Greenway and road diversions before you set off.
The story
Decades in the making
People have talked about bridging the water at Narrow Water for generations. An earlier attempt stalled in 2013 when the funding fell through, before the Irish Government’s Shared Island Fund brought it back to life, and construction finally began in 2024.
For the towns on both shores, it means a short hop instead of a long way round, and a chance to welcome visitors to both sides of the lough in a single day.
Narrow Water also carries painful history. In August 1979, 18 soldiers were killed in an attack at Narrow Water, and the place means different things to different people. Many hope the bridge will become a symbol of connection, built with that history in mind.
Make a day of it
Come for a look at the bridge, then stay for the castle, a walk on the prom and a bite to eat in Warrenpoint.

History & Heritage · Warrenpoint
Narrow Water Castle
Historic 16th-century tower house overlooking Carlingford Lough.

Cafés · Warrenpoint
Bric Cafe
Popular coffee spot known for quality coffee and relaxed atmosphere

Accommodation · Warrenpoint
Whistledown Hotel
Seafront hotel overlooking Carlingford Lough with restaurant and bar

Pubs & Bars · Warrenpoint
Victoria Pub Warrenpoint
Traditional pub in the centre of Warrenpoint known for functions, drinks and live music
The County Down Craic · every Thursday
Get bridge updates in The County Down Craic
The big local story, what’s on, a hidden gem and a bit of craic. Every Thursday, free.
Narrow Water Bridge: your questions
When will the Narrow Water Bridge open?
Main construction is due to finish in late 2027, with the bridge expected to open in early 2028 after testing. No opening day has been confirmed yet. We update this page as the project announces new dates.
Where is the Narrow Water Bridge?
It crosses the Newry River where it meets Carlingford Lough at Narrow Water, near Warrenpoint and Narrow Water Castle on the County Down side, linking to Cornamucklagh near Omeath on the County Louth side.
Will there be a toll?
No. The project says no toll is currently envisaged on the bridge or its access roads.
Can you walk or cycle across it?
Yes. It’s designed for walkers and cyclists as well as traffic, with a barrier separating them from vehicles and a ramp linking it to the Carlingford Lough Greenway.
Does the bridge open for boats?
Yes. One of its two spans lifts on a rolling mechanism to let boats through to Newry. While it’s opening, barriers stop traffic, walkers and cyclists from crossing.
How long is the bridge?
About 195 metres, in two spans. Some older reports quote 280 metres, which included more of the wider scheme; the current project describes the bridge itself as about 195 metres.
Who is building it and who is paying?
Louth County Council leads the project, BAM is the main contractor and Roughan & O’Donovan designed it. The Irish Government’s Shared Island Fund is paying for the €102 million (plus VAT) construction contract, with the Northern Ireland Department for Infrastructure as a partner.
Is the Carlingford Lough Greenway closed?
A section near the works is closed to walkers and cyclists while the heavy lifting goes on, with signposted diversions. Check the official project notices before you set off.
Where can I watch the bridge being built?
The Warrenpoint seafront and the Newry Road near Narrow Water Castle give good views of the site, and the barges arrive into Warrenpoint Harbour. Please stay out of the works area and park considerately.
Who’s involved, and where our facts come from
- Louth County Council: Leads the project and will look after the bridge
- Shared Island Fund (Irish Government): Pays for the construction contract
- Department for Infrastructure (NI): Northern Ireland partner
- BAM: Main contractor, building it
- Roughan & O’Donovan: Lead designer, supervising the build
- Narrow Water Bridge project (official site)
- Project FAQs
- BAM: first barge arrives
- RTÉ: component arrives in Warrenpoint Harbour (Oct 2026)
- Department for Infrastructure: construction begins
- gov.ie: construction commences
Last checked 20 November 2026. Dates and details can change: check the official project site for notices.